| On Monday, June 3, 2002, the footings were finally poured to hold the
foundation walls for our new parish center. |
 |
 |
 |
 |
| Facing Pine Street, one can see the back of
the school building and the footings that are in line for the foundation
and retaining wall for the parking lot. |
Looking from the parking lot toward the
school, one can see the far corner of the new building and the area
between the school and center that will be a secure outdoor area. |
Another angle looking from the corner closest
to the rectory and across the new building area toward the brick
school. The door in the distance leads to the cafeteria. |
From the front corner of the rectory, looking
across the site toward Pine Street. |
| The trucks arrive to pour the footings for
the foundation. There were six trucks and a total of 57 square yards
of concrete. |
 |
 |
|
| As the weeks continue, the forms
and other work progresses for the foundation of a new parish center. |
| On Monday, June 24, 2002, the foundation
wall that also serves as a retaining wall to the parking lot under construction in the above
photographs was poured. |
 |
 |
 |
 |
| A crane with a pump was brought in to
move the concrete up and into the forms. |
This pump was connected to each cement truck
as it emptied its cargo into the forms for the walls. |
The workers from Bay State work to vibrate
the concrete to remove air pockets and assure that all the space is filled
with concrete. |
Another angle of the job underway. |
 |
 |
 |
 |
| This is taken form the corner of the new
building closest to the school. It shows the back wall, at the far
end is the sacristy area for a new chapel. |
This is taken from the opposite end of the
building. Here you can begin to see how the new building will line
up exactly with the back wall of the existing school. The forms you
see are for the back wall of the sacristy. |
This is taken from inside on the ground
level. This is looking toward the church and is the area that will
be the foundation for the chapel and sacristy area. |
This is at the other end of the building, the
school can be seen beyond. The forms to the left are for a building
foundation, more to the right is the retaining wall for the service area
between the buildings. |
 |
 |
 |
 |
| This is the area between the buildings.
Eventually this will all be filled to grade and will be an area that will
provide a driveway that can serve for service deliveries and trash
removal. It's hard to imagine that it will be wide enough for
sidewalks and a drive. |
This is a look down into the excavation for
the area between the buildings. The large box shape is the pit for a
service elevator to access deliveries to the ground level. |
This is a close-up of the service elevator
area. The bars at the front of the picture will eventually be a
concrete wall. The footings and bars to the left are for a frost
wall for the school. |
This a shot looking back at where the
previous three pictures were taken. The rods to the right will form
a new frost wall for the school The space in the middle of the photo
will be the location for a new stairwell to reach the cafeteria. |
 |
 |
 |
 |
| Above is pictured the footing for the right
front corner of the building, closest to Hamilton Street. This area
of the building will house the parish offices on the first floor. |
A larger view of this footing area, showing
the front line of the building as it moves right toward the top of the
photo. This is to accommodate a stairwell from the second floor. |
This is the service area between the
buildings. The foundation for the building is to the right, the
school is to the left. The ladder is against the shaft for the
freight elevator. |
This is looking at the area pictured in the
left photo from the other end, notice that now the school is on the
right. The freight elevator will be used to bring supplies and
equipment from the street to lower level. |
 |
 |
 |
 |
| This is the foundation and retaining wall
sprayed for water protection and covered with insulation fiber. |
A view of the footings for the foundation
wall that is the corner nearest to the rectory and Hamilton St. |
A look across the site toward the school,
with a view for the inside of the foundation wall. |
A closer look at the work nearest the present
school building. The large shaft to the left is for the freight
lift. |
 |
 |
 |
 |
| A closer look at the freight lift
shaft. This view is looking toward the parking lot. |
A step back to take in the progress on the
site. The school is to the right, the freight lift is ahead, between
them will be stairs to access the lower level. |
A view across the site, looking toward the
rectory. The walls and the parking lot are to the right. On
the left are the footings that are under construction. |
A closer look at the footings that will be
for the front of the building as it faces Hamilton Street. |
 |
 |
 |
 |
| With the foundation sealed against water and
insulated the backfilling begins. Once this area is filled in, it
will become part of the parking lot with enough space for a sidewalk
against the building. |
A look across the building site near where
the door from the parking lot. The footings are for the front
wall of the building that will face Hamilton Street. Beyond those
are forms for a retaining wall. |
This view is from the front corner near the
rectory across the site. The forms are placed for the wall nearest
to the school. The lower form in the middle is for a doorway, that
is about where the floor will be located. |
This is a more direct view of these footings,
looking toward the school. The forms to the right will be for a
footing for the stairway that will be an exit from the second floor and
pass through with a ramp to the cafeteria. |
 |
 |
 |
 |
| This view is the service area between the
buildings. The forms that are braced are for a frost wall to protect
the footings of the school building. |
This is the same area as to the left, but
from the other side. The closest right hand corner is the door to
the cafeteria. The space between the footing and the elevator is for
stairs. |
Take a turn toward Hamilton Street, this shot
shows the beginnings of the forms for the new building and some of the
piers that will hold the terrace for the main floor. |
This is another view of the footings for the
wall that will face the cafeteria and gym. Again the lower area of
the footing is for a door and that height is where the floor will be.` |
 |
 |
 |
 |
| A view of the footing for the
front stairs. This is the side closest to the building.
Between this and the wall is a ramp into the basement. |
A look from the door near the
cafeteria toward the parking lot. The wall to the right is a frost
wall for the school's foundation. The space between will be a
staircase. |
Paul of ABC, Inc. lends a 'heavy'
assist to the installation of the water line for the new building.
This is a copper pipe that is 2 inches in diameter. A coil is seen
in the back. |
A look across the work
site. The forms at the front right are the southeast corner of the
building where the parish offices will be located on the main floor. |
 |
 |
 |
 |
| Here is where the water line
enters this building. This point will be capped with a valve and
then feed water to the rest of the building. |
A look at the water line running
from the street alongside the building before it turns to enter the
foundation at the location where the utilities will be located. |
A view along the front of the
building where the front wall of the building will be located. |
A look across the building site
from the corner nearest the parking lot and school. |
 |
 |
 |
 |
| With the forms removed a shot of
the frost wall to protect the school foundation. |
A view from the back of the
rectory looking uphill. The backfill now shows where the new parking
lot will be. |
This is the transformer area of
the school that is being replaced. These will be removed and placed
on a slab near the parking lot. |
Another view across the building
site showing the progress of work as of August second. |
 |
 |
 |
 |
| Looking across the building site,
one wall of the foundation remains to be completed. |
A look down from above showing
the footings for the steel piers inside the building. |
The new utility pole, finally
installed after being delivered on Good Friday. This will carry
utilities from the street to the center, and the school also. |
The location of the previous
transformer, installed during the construction of the present school in
1959. This service will be upgraded as a result of this
construction. |
 |
 |
 |
 |
| A shot of the conduits that are
buried beneath the parking lot to carry the utilities to the buildings. |
A view of the service area to be
located between the buildings. The reinforcement rods are for a
retaining wall to hold the service alley and provide access for a stairway
to the cafeteria door. |
A view across the building site
to gain a perspective of the scope of the work and progress that is made
on a daily basis. |
Another view of the building
site. This one is taken from the right front corner, near the
school's Hamilton St door and looks across toward the church and parking
lot. |
 |
 |
 |
 |
| A view at the front of the
building as the footings for a retaining wall and the front stairs are in
place. |
A wider shot of the footings for
the passageway and the stairs that will provide access from Hamilton St to
the main floor. |
A look outside the retaining wall
to the work that will eventually be buried. This is a photo of the
perimeter drain and tie-ins for water and fire to the street service. |
As the foundation is backfilled
to the height of the basement level, the building begins to become
apparent and the site begins to reveal our future building. |
 |
 |
 |
 |
| A shot across the building site
to give perspective of the building. The large pit in the center is the
footing for the future elevator. |
A look across the building site
from the opposite corner. The far end will be the last section of
the foundation closed to provide access for the cement trucks to other
areas of construction. |
A view of the area between the
buildings, looking toward the cafeteria. Eventually, this level will
be covered with a cement terrace above. The footings for the terrace
are visible. |
A view from the corner of the
mechanical room toward the area between the buildings. The cement
squares are for the steel supports for the terrace to be located above. |
 |
 |
 |
 |
| A view of the construction site
as the crew works on filling the grade inside the foundation to the
required level. |
Another view of the construction
site looking the other way. The grade is rising above the
level of the footings for the floor. |
A view from the outside in.
From the front of the building, looking past the footings for the basement
ramp into the basement floor level. |
A photo of the inside of the
building. In the foreground is the footing for the elevator. |
 |
 |
 |
 |
| The four photos
above show progress on the front steps to the building. The access
will be to the side nearest the rectory with a curved stairway leading to
a porch area. Between the steps and the building there is a
retaining wall for a ramp and then between the ramp and the stairs up,
another flight of stairs down to a door at the basement level. These
photos are taken from the rectory side. |
 |
 |
 |
 |
| This is the passageway at the
front of the building to allow access around the building between the
school and playground. Hamilton Street is to the left. |
This is a view of the front right
hand corner of the building and the space between the new center and the
present school. This area will be covered eventually. |
Panning to the right from the
photo to the left of this, the school's kitchen windows come into
range. Ahead is the freight lift and the passage for the stairs. |
This view is inside the building
where the mechanical room will be sited. The utilities are roughed
in, viewed by the pipes in the wall and the water to right. |
| The work
photographed preceding this has been completed as of September 1, 2002.
The following photos show work completed as of September 8, 2002.
|
 |
 |
 |
 |
| At the front of the new center,
looking toward the school. The stairway is to the right, to the left is
the retaining wall for the ramp, the foundation wall is to the far left.. |
Looking across the building site
from the corner near the front of the rectory. Within the building
site are the footings for column piers and the elevator. |
Looking toward the back from the
same angle, the floor level of the building is more noticeable and the
preparation work for the steel columns and elevator. |
Looking from the rear corner near
the rectory, this is the last of the foundation wall to be
installed. One can see that the earth that was a ramp is being moved
in preparation for the footing. |
 |
 |
 |
 |
| A view across the building site
showing the foundation complete. |
Another view from the side near
Hamilton Street and toward the far corner with the last area of the
foundation now in place. |
A view of the building showing
the area where the restrooms will be located and the plumbing already
roughed in. |
A view from the outside corner
near the rectory showing the completed foundation, this area is where the
door from the parking lot will be located. |
 |
 |
 |
 |
| A shot of the shaft for the
elevator. From here the three doors for each of the floors are
visible. |
A side view of the elevator
shaft, taken from the parking lot. The slots in the shaft are for
the steel beams to be inserted. |
Another view of the elevator
shaft, this angle, is from near the entrance door and looking across the
area that will be the hallway. |
A view of the beginning of the
new drainage system for the parking lot. Some ledge has held up the
installation of parts of the system. |